Khazrabad III 100 MW Solar Power Plant Project (in cooperation with SATBA)

The Khazrabad III 100 MW solar power plant project has been defined in cooperation with the Renewable Energy and Energy Efficiency Organization (SATBA) as part of efforts to expand renewable energy capacity.

Khazrabad III 100 MW Solar Power Plant Project (in cooperation with SATBA)
Power Sector Development Projects

Khazrabad III 100 MW Solar Power Plant Project (in cooperation with SATBA)

The Khazrabad III 100 MW solar power plant project has been defined in cooperation with the Renewable Energy and Energy Efficiency Organization (SATBA) as part of efforts to expand renewable energy capacity. The project is also planned within the framework of the national program to develop 7,000 MW of renewable power plants through resources from the National Development Fund, in line with the President’s emphasis on expanding clean energy.
The project will be implemented on an 80 hectare site adjacent to Chadormalu’s first solar power plant. The execution model is planned as EPC+F (Engineering, Procurement, Construction plus Financing). The electricity generated by this plant will be sold through the Energy Exchange.
The project’s implementation period is estimated at approximately five months. Initial steps have already been taken to advance the project, including the signing of an agreement with SATBA, the selection of the project site, and securing the company’s equity contribution for project financing.

  • Project typePower Sector Development Projects
  • Project statusReady for Groundbreaking
  • LocationAshkezar County, Yazd Province
  • The Khazrabad III 100 MW solar power plant project has been defined in cooperation with the Renewable Energy and Energy Efficiency Organization (SATBA) as part of efforts to expand renewable energy capacity. The project is also planned within the framework of the national program to develop 7,000 MW of renewable power plants through resources from the National Development Fund, in line with the President’s emphasis on expanding clean energy.

    Technical Specifications

    The project will be implemented on an 80-hectare site adjacent to Chadormalu’s first solar power plant. The execution model is planned as EPC+F (Engineering, Procurement, Construction plus Financing). The electricity generated by this plant will be sold through the Energy Exchange.

    Scope of Work

    The project will be implemented on an 80-hectare site adjacent to Chadormalu’s first solar power plant. The execution model is planned as EPC+F (Engineering, Procurement, Construction plus Financing). The electricity generated by this plant will be sold through the Energy Exchange.

    Project Timeline

    1. لورم ایپسوم1405/04/15

      لورم ایپسوم متن ساختگی

    2. لورم ایپسوم1405/04/16

      لورم ایپسوم متن ساختگی

    3. لورم ایپسوم1405/04/24

      لورم ایپسوم متن ساختگی

    4. لورم ایپسوم1405/04/27

      لورم ایپسوم متن ساختگی

    Achievements

    The project’s implementation period is estimated at approximately five months. Initial steps have already been taken to advance the project, including the signing of an agreement with SATBA, the selection of the project site, and securing the company’s equity contribution for project financing.